Alternative Earthwork Strategy in MX Road

$
0
0

Hi All,

Let, I want to define 5 alternative slopes for filling as below: 

Slope 1: To be used if the calculated height is below 2m

Slope 2: To be used if the calculated height is between 2m to 3m

Slope 3: To be used if the calculated height is more than 3m

Slope 4: To be used if the calculated height is more than 4m

Slope 5: To be used if the calculated height is more than 5m

My question is that where do we define these height criteria which is to be taken into consideration by MX to apply appropriate slope.